Saturday, August 23, 2008

Calendar

3-D Concepts, ART 2757 Fall 2008 Calendar

Instructor: Stephanie Stuefer

DATE

AGENDA

HOMEWORK

Monday

August 25

-Introduction & orientation

-Review blog

-Introduce Project 1

- Buy clay tickets and tools

-Read assigned text for Project 1

Wednesday

August 27

DEMO: Coil, slab ,pinch

-Distribute clay

-Make testiles and work on Project 1

-Work

Monday

September 1

NO CLASS-LABOR DAY

-Work-complete building

Wednesday

September 3

DEMO: Surface Techniques, glazing

-Powerpoint

-Work on Project 1

-Load testiles bisque

-Work on Project 1

Monday

September 8

-Work on Project 1

-Work on Project 1

Wednesday

September 10

-Finish building Project 1

Complete leather hard stage surface treatments, allow Project 1 to dry over weekend

Monday

September 15

Project 1 Extension

-See Project 2 sheet for research and sketchbook assignments

Wednesday

September 17

Load Project 1

-Begin Project 2 Research and Sketch Assignments

Monday

September 22

Check in at 11:45, finish presentations (library/sketching), then meet in groups at 2pm to present research and sketches

-Begin Project 2 maquettes

Wednesday

September 24

-Maquette critique

-Begin building Project 2

-Work on Project 2

Monday

September 29

-Load Project 1 glaze

-Load Project 2 maquettes bisque

-Work on Project 2

-Prepare Project 1 for critique

Wednesday

October 1

-Unload Project 1 and Project 2 maquettes

-Project 1 Critique

-Work on Project 2

Monday

October 6

-load Project 2 maquette glaze

-workday Project 2

-Work on Project 2

Wednesday

October 8

-workday Project 2

-Finish building Project 2, allow to dry over weekend

Monday

October 13

-Load Project 2 bisque

-Indroduce Project 3

-Powerpoint

-Work on Project 3 readings, sketches and maquettes,

Wednesday

October 15

-Unload Project 2

-Glaze Project 2

-Finish glazing Project 2

-Work on Project 3 sketches and maquettes

Monday

October 20

-Load Project 2 glaze

-Project 3 maquettes and sketches due

-Work on Project 3

Wednesday

October 22

-Unload Project 2

-Project 2 Critique

-Work on Project 3

Monday

October 27

-Project 3 workday

-Load Project 3 maquettes

-Work on Project 3

Wednesday

October 29

-Unload Project 3 maquettes

-Project 3 workday

-Finish building Project 3, allow to dry over weekend

Monday

November 3

-Project 3 Workday

Review Project 4 Sheet on Blog

Wednesday

November 5

-Load Project 3 bisque

-Introduce Project 4

-Work on Project 4

Monday

November 10

-Unload Project 3 bisque

-Work on Project 4

-Work on Project 4

Wednesday

November 12

-Glaze Project 3

-Work on Project 4

-Finish glazing Project 3 for loading on Saturday

-Work on Project 4

Monday

November 17

-Work on Project 4 and testiles

-Work on Project 4, finish testiles

Wednesday

November 19

-Project 3 Critique

-load Project 4 testiles

-Finish Project 4 and allow to dry over weekend

Monday

November 24

-Load Project 4 bisque

-Load Project 4 testiles glaze

Wednesday

November 26

NO CLASS

Happy Thanksgiving!

Monday

December 1

-Glaze Project 4

-Finish Glazing Project 4

Wednesday

December 3

-Load Project 4 glaze

-Prepare Project 4 for Critique

Monday

December 8

Final Crits

Wednesday

December 10

Final Crits-Class Party

No comments: